2 January 2001.
The steel roof trusses are still being installed, though hampered by zero degree weather and high winds over the past weeks.  The steel supports for the tower appear to be almost complete, ready for the towersteel to be erected.  This photo is deceiving in that there is over12" of snow on the ground, and though blue skies and sunshine prevails,it is still very cold.  Friday and Saturday of this week is supposed to bring in warmer weather above the freezing level which hopefully willallow for the completion of the steel roof trusses and allow the construction workers to start on the roof itself.

The stone masons have arrived, and as soon as the weather permits, should start installing the 8 ft. sections of stone on the sides of the Temple.  Natural gas heaters are used to heat the basement through the third floors at this time, with the fourth and fifth floors still exposed.  Inside many things are happening.  The font and basement areas are stillbeing worked on.  The interior framing has begun with drywall justbeing started.  The stairs are still being poured in the front cornersof the Temple, which is very involved since the North West stairway isa circular stairway, with elevator shafts.  Many of the Windows arecomplete, being built in Nauvoo by Charles Allen at the Allyn House and will be installed after the stone is in place.  Electrical work, plumbing, sprinklers, alarms and other utilities are currently being installed.


 Construction workers are back  on the job, rebuilding theTemple after a holiday break.
2 January 2001


January 6th 2001.  Structural steel complete for the bell tower,the whole scene in the roof is the access way into the bell/clock tower,for maintenance access.  A ladder will be erected for the maintenance personnel to enter.  Concrete will be poured above the ribbed steelcreating the roof for the attic box and the base for the bell/clock tower.
 


  The generator that will supply all backup electricity for theTemple.


  Steel re-bar being lifted by crane to the fifth story roof for reinforcement in the concrete.


8 January 2001.  Window removed to load building materials into temple.


  8 January 2001.  Scott Downs, currently from Nauvoo, using a transit to mark the final stone elevations on the wall of the Temple. Steel supports are being anchored to the walls in preparation for the firstrows of hand laid limestone blocks.  The hand laid limestone blockswill be placed up to the first  floor level or approximately where the concrete color changes in this photograph.

 15 January 2001 the attic box fifth story roof has been pouredand sealed in with clear plastic to retain the heat.


15 January 2001


15 January 2001


  15 January 2001


15 January 2001  Computer enhance photograph of the stainlesssteel supports anchored to the temple concrete walls in preparation forstone that should arrive the end of this week.


  15 January 2001.  With the weather a bit milder, construction picks up pace.  Inside basement and font area partitions are beinginstalled with wiring and plumbing following close behind.  The Celestialroom is about ready for the modified steel trusses to the installed whichwill close in the room structurally.  The approximately 40 ft. tallroom is at the third floor level, but extends through the fourth floorand into the attic on the East end of the building.  This should makea spectacular room with its period decor and woodworking.  Stone workis to begin just after the first load of stone arrives from Salt Lake City,sometime around the 19th or 20th of January.


01/20/01  Concrete being pumped through the second story spiralstaircase window, pouring the spiral stairway steps up to the second floor.


01/20/01   Front temple stairs being formed for concrete.


01/20/01


01/26/01   Delivery trucks from St. Louis arrive to deliversteel wall partition framework and drywall.
 


01/26/01 Legacy Constructors crew remove plywood from window openingsfor delivery of drywall and steel petition framework.  The petitionframework was delivered to the second and third floors, with drywall deliveredto the first four and basement.


  26 January 2001


26  January 2001.  Roof framework above celestial room nearcomplete as viewed through large attic area window.


26 January 2001.  Roof framework seen through attic window.


26 January 2001.  Overhead hoist system installed to set heavystone in place.  Some stone has  arrive on site as of thisdate. Steel studs being loaded into 3rd story window.
                                
 26 January 2001.Open windows into the North side of the Temple.  Taken from three different angles, much can be seen of the interior ifyou carefully study the details.  On the left photograph in the topwindow the third story support column can be seen that will be in a partitionwall in a series of rooms that will lead to be celestial room.  Thebottom window openings show scaffolding that is being used for wall andceiling work in the first floor area.  In the right photograph inthe top window the opening for the celestial room that goes completelyup to the attic can be seen.  As the other photographs taken thisdate show that the roof itself is now steel framed, but still open.
 

NauvooTemple Construction Animation
 

Please E-Mail us for your comments on this page

  LastUpdated   25 May 2004

  RETURN TO HOME PAGE

  VIEW OTHER MONTHS

   RETURN TO NAUVOO INTERNET NEWS

Published by Fred Cote
Nauvoo Illinois

  ©  Copyright 2004 Fred Cote, all rights reserved